H.R. 10988: the bill

[Congressional Bills 119th Congress]
[From the U.S. Government Publishing Office]
[H.R. 10988 Introduced in House (IH)]

<DOC>






119th CONGRESS
  2d Session
                               H. R. 10988

To amend the Federal Power Act to direct the Federal Energy Regulatory 
 Commission to require that public utilities use advanced transmission 
    technologies when carrying out certain projects, and for other 
                               purposes.


_______________________________________________________________________


                    IN THE HOUSE OF REPRESENTATIVES

                           November 10, 2026

 Mr. Vindman introduced the following bill; which was referred to the 
                    Committee on Energy and Commerce

_______________________________________________________________________

                                 A BILL


 
To amend the Federal Power Act to direct the Federal Energy Regulatory 
 Commission to require that public utilities use advanced transmission 
    technologies when carrying out certain projects, and for other 
                               purposes.

    Be it enacted by the Senate and House of Representatives of the 
United States of America in Congress assembled,

SECTION 1. SHORT TITLE.

    This Act may be cited as the ``Lower Electricity Bills Act''.

SEC. 2. ADVANCED TRANSMISSION TECHNOLOGIES.

    (a) In General.--Part II of the Federal Power Act (16 U.S.C. 824 et 
seq.) is amended by adding at the end the following:

``SEC. 224. USE OF ADVANCED TRANSMISSION TECHNOLOGIES.

    ``(a) Definitions.--In this section:
            ``(1) Advanced transmission technology.--The term `advanced 
        transmission technology' has the meaning given the term in 
        section 1223(a) of the Energy Policy Act of 2005 (42 U.S.C. 
        16422(a)).
            ``(2) Best-available transmission conductor.--The term 
        `best-available transmission conductor' means a transmission 
        conductor that, as determined by the Commission--
                    ``(A) provides the greatest feasible and 
                commercially available energy-carrying capacity at a 
                given voltage level;
                    ``(B) provides the highest feasible and 
                commercially available electrical efficiency at that 
                voltage level; and
                    ``(C) provides the greatest available level of 
                mechanical performance, including mitigating thermal 
                sag at the maximum rated transmission-carrying capacity 
                of the applicable transmission facility.
            ``(3) Commission.--The term `Commission' means the Federal 
        Energy Regulatory Commission.
            ``(4) Covered project.--The term `covered project' means 
        the construction of a new transmission facility, or the 
        modification, upgrade, replacement, or reconductoring of an 
        existing transmission facility, subject to the jurisdiction of 
        the Commission under section 201(b).
    ``(b) Use of Advanced Transmission Technologies.--In exercising its 
authority under sections 205 and 206, the Commission shall require that 
public utilities use advanced transmission technologies, including 
best-available transmission conductors, when carrying out covered 
projects.
    ``(c) Presumption of Prudence for Advanced Transmission 
Technologies.--In any filing seeking to recover the cost of an advanced 
transmission technology for a covered project, and in any proceeding to 
determine whether that cost may be recovered through rates, the 
Commission shall presume that--
            ``(1) the use of an advanced transmission technology is a 
        prudent practice; and
            ``(2) the costs associated with the use of an advanced 
        transmission technology are just and reasonable.
    ``(d) Applicability.--The requirements of this section apply only 
to public utilities and only with respect to covered projects.
    ``(e) Rulemaking.--
            ``(1) In general.--Not later than 1 year after the date of 
        enactment of this section, the Commission shall issue an order 
        or rule to implement this section.
            ``(2) Requirements.--In issuing an order or rule under 
        paragraph (1), the Commission shall--
                    ``(A) require that public utilities conduct, on 
                Commission-established timelines, recurring 
                evaluations--
                            ``(i) to determine whether the benefits 
                        associated with deploying advanced transmission 
                        technologies through 1 or more covered 
                        projects, including benefits to the current 
                        transmission system of the applicable public 
                        utility, outweigh the costs (such that the 
                        applicable benefit-cost ratio is greater than 
                        1);
                            ``(ii) that include a least-cost analysis 
                        with respect to the transmission system of the 
                        applicable public utility; and
                            ``(iii) that evaluate whether the costs for 
                        which recovery is sought reflect due care to 
                        minimize the total cost of the applicable 
                        covered projects;
                    ``(B) require public utilities to conduct, on 
                Commission-established timelines, recurring evaluations 
                to consider planning and construction timelines for new 
                transmission assets and risks and impacts of potential 
                delays;
                    ``(C) require that, if the benefits of 1 or more 
                advanced transmission technologies outweigh the costs 
                (such that the applicable benefit-cost ratio is greater 
                than 1), the applicable public utility shall deploy the 
                advanced transmission technologies on a timeline 
                determined by the Commission;
                    ``(D) require that decisions on whether to 
                implement advanced transmission technologies based on 
                the recurring evaluations under subparagraphs (A) and 
                (B) are reported to the Commission, in a manner 
                determined by the Commission;
                    ``(E) in consultation with the Secretary of Energy, 
                establish a methodology for determining whether a 
                transmission conductor is a best-available transmission 
                conductor for purposes of this section;
                    ``(F) ensure that the methodology established under 
                subparagraph (E) is consistent with the criteria 
                described in clauses (i) through (iii) of subparagraph 
                (A);
                    ``(G) provide for periodic review and updating of 
                the methodology established under subparagraph (E) not 
                less frequently than annually to reflect improvements 
                in technology, materials, and system performance; and
                    ``(H) determine a penalty for any public utility 
                that fails to deploy the relevant advanced transmission 
                technologies when the applicable benefit-cost ratio is 
                greater than 1 in a timeframe determined by the 
                Commission, including a reduction of the effective 
                return on equity for the transmission system of the 
                public utility.''.
    (b) Definition of Advanced Transmission Technology.--Section 
1223(a) of the Energy Policy Act of 2005 (42 U.S.C. 16422(a)) is 
amended--
            (1) in paragraph (18), by striking ``and'' at the end;
            (2) by redesignating paragraph (19) as paragraph (23); and
            (3) by inserting after paragraph (18) the following:
            ``(19) dynamic line rating;
            ``(20) advanced power flow control;
            ``(21) transmission topology optimization;
            ``(22) high-performance conductors; and''.
                                 <all>